BitFuFu Inc. (“BitFuFu” or the “Company”) (NASDAQ: FUFU), a global leader in Bitcoin mining and comprehensive mining services, today announced its unaudited production and mining operations updates for March 2025.


Key Highlights:

 * Bitcoin Holdings: Held 1,847 Bitcoins ("BTC") as of March 31, 2025, increased by 47 BTC compared to the balance as of the end of February 2025.

 * Bitcoin Production: Produced 234 BTC, including 58 BTC from self-mining operations and 176 BTC for cloud-mining customers.

 * Miner Energization: Except that a portion of miners were sold to customers, most of the 2,000 S21 XP miners ordered in November 2024 and the 4,000 S21+ miners ordered in December 2024, have finished energization in the Company’s secured datacenters in U.S. as of the end of March 2025, adding 1.1EH/s self-owned mining capacity to the Company’s management hashrate network.


“We accelerated the energization of our self-owned S21 series miners in March 2025, adding over 1 EH/s of highly efficient self-mining hashrate, amid ongoing market volatility,” said Leo Lu, Chairman and Chief Executive Officer of BitFuFu. “As global macroeconomic risks mount, Bitcoin’s resilience as a store of value is becoming increasingly evident. With one of the most efficient mining fleets in the industry and a fast-paced vertical integration strategy, we are rapidly reducing our operating costs and strengthening our competitive edge.”


Bitcoin Holdings and Production:

 * BTC Held: 1,847 BTC as of March 31, 20251, increased by 47 BTC compared to the balance as of the end of February 2025.

 * Self-Mining Production: 58 BTC, unchanged from February 2025.

 * Cloud-Mining Production: 176 BTC, representing a 9% increase from February 2025.


Hashrate Management:


 * Total Hashrate Under Management: 20.6 EH/s as of March 31, 2025.

  - Self-Owned Hashrate: 4.2EH/s, increased by 1.1EH/s or 35% compared to last month as the Company self-owned S21 series miners purchased in the fourth quarter of 2024 were energized in March 2025.

  - Cloud-Mining and Co-Hosting: 16.4 EH/s.


 * Miner Energization:

  - Except that a portion of miners were sold to customers, most of the 2,000 S21 XP miners ordered in November 2024, and the 4,000 S21+ miners ordered in December 2024, have finished energization in the Company’s secured datacenters in U.S. in March 2025.


Power and Facilities:

 * Power Under Management: 478 MW total hosting capacity.


Mining Services:

 * Cloud-Mining Growth: Registered users reached 607,377 as of March 31, 2025.


Upcoming Conferences & Events:

 * April 16, 2025: Company to present at Jefferies Power x Coin Virtual Conference.

 * May 27-29, 2025: Company to participate and present at Bitcoin 2025 in Las Vegas.

 * May 29, 2025: Company to present at Lytham Partners Spring 2025 Investor Virtual Conference.